Date: Monday, 30 June 2025

uMngeni-uThukela Water (UUW) hereby informs all affected stakeholders of a planned 16 hour emergency water supply shutdown from the Lower Thukela Waterworks to KwaDukuza. The shutdown will start at 06h00 on Wednesday until 22h00 on the same day.

This interruption is necessary to carry out urgent pipeline repairs over the Stanger River Bridge. During the shutdown, the following critical maintenance activities will be conducted:

The shutdown is scheduled to proceed unless disrupted by adverse weather conditions. A final confirmation of the shutdown will be issued by the afternoon of Tuesday, 01 July 2025, should any changes become necessary.

Affected Areas:

We sincerely apologise for the inconvenience caused and appreciate your patience and understanding during this essential maintenance operation.